PROJECT OVERVIEW

HV work for Wave Park, Melbourne Airport  – this project involved the installation, testing and commissioning of  HV cabling and associated civil works and Substation 124 and Substation 125

The work included:

  • supply and installation of conduits and box culverts
  • supply and installation of earth grids
  • construction of kiosk concrete slabs
  • off load and install new kiosks substations 124 and 125